Rollout monitoring

Dashboard

Overall Productivity63%Actual cable vs rollout plan
Cable Progress38,825 m61,600 m planned
Box Deployment333HUB, SUB, END and XBOX records
Actual / Passed Users4,635Fictional passed premises
Open Issues3Operational notes requiring action
Schedule Variance-4%Actual minus planned average

Project Health

Watch
North District A69 / 100
69%

Design vs Field Validation

17 elements
Box Match9Installed as planned
Mismatch4Length or code differs
Missing3Not reported from field

Network Element Progress

HUB4 / 18
22%
SUB26 / 76
34%
END325 / 384
85%
XBOX36 / 92
39%
Cable38,825 / 61,600
63%

Priority Issues

Recent Activity

Cable record validated2026-08-29 14:20 - North District A

CBL-24F-008 length variance sent to validation review.

END boxes installed2026-08-29 12:10 - Central Zone B

Eight END boxes added to Central Zone B rollout records.

Priority issue opened2026-08-29 10:45 - West Sector C

Route obstruction added for West Sector C.

Distribution unit installed2026-08-28 16:30 - East Sector D

XBOX-022 submitted for network validation.